West Hatch High School, Chigwell
Project Value – £800k
Project Duration – 43 Weeks
Project Description;
Construction of new sports hall on existing school facility inc completion of outstanding works from previous main contractor
Scope of Works;
- Completion of foundations for new sports hall
- Completion of deep storm drainage including installation of very large attenuation tank
- Rectification of installed foul drainage including within existing buildings where slabs and beam and block floor had to be removed to enable install
- Construction of retaining walls and associated waterproofing details
- Full externals package