SEGRO Park Plot 70
Dagenham
Full groundworks package, inclusive of earthworks, drainage, services, foundations and external works for a 13 unit speculativeley built industrial scheme.
38 Weeks
£1.5m
Lok 'N' Store
Stevenage
Full groundworks package for the new build construction of a Lok 'N' Store self storage facility. Works consisted of earthworks, foundations, drainage, services and external works
29 Weeks
£900k
Fujifilm
Bedford
Construction of a new workshop and office facility for Fujifilm. Works consisted of foundations, drainage and services, along with the construction of a large block paved car park.
37 Weeks
£1m
Bloom Brixton
Brixton
Construction of 5nr ultra-urban industrial units along with two concrete yards. Package consisted of piled foundations, drainage, services and all external works inclusive of the concrete yard slabs
52 Weeks
£1.3m
Alcohols
Rugby
Construction of a new distillery facility for Alcohols ltd. Consisting of all sub-structure work for multiple units (office / Distillery / Warehouse), Drainage works including large attenuation tanks and rainwater harvesting systems and external works package
39 Weeks
£2m
CMR Surgical
Ely
Construction of new 75,000sqft robotic surgical equipment facility for CMR surgical, with extensive external parking and concrete yard area.
42 Weeks
£2.2m
West Hatch High School
Chigwell
Completion of groundworks to new school facilities after the original main contractor went in to administration. Including completion of drainage and services works and full externals package.
43 Weeks
£800k
Biggin Hill Airport
Biggin Hill
New hotel alongside the existing airport. Works consisted of mass pour foundations, all drainage and services works and full externals package inclusive of permeable parking facilities.
60 Weeks
£1.3m
St Catherines Hospice
Crawley
Construction of a new hospice care facility in Pease Pottage, Crawley, Consisting of reinfroced ground beams on piled foundations, and full external works package with enclosed ndecorative court yards etc
64 Weeks
£2m
Travel Lodge
Chiswick
New build construction of a 113 bed travel lodge on Chiswick High road, sandwiched between a car dealership and a foreign embassy. including piled foundations, drainage, services and external works package.
81 Weeks
£600k
Magenta Storage Solutions
Acton
Construction of a new build storage facility in ACtion, including a tight front concrete yard with associated drainage etc
43 Weeks
£400k
Dry Street Primary School
Basildon
Construction of a new primary school on a new build estate in Basildon. Works consist of raft concrete slab, all drainage/services works and full external works package including new MUGA pitch facilities.
52 Weeks
£1.7m
Les Lion Polo Club
Maidenhead
Construction of new facilities to an existing polo club, including 2nr new buildings, increase in parking facilities and new external social spaces
24 Weeks
£500k
Thornhill Primary School
Houghton Regis
Constructionolf a new passivehaus primary school, with deep mass pour foundation on a formed stone plateau, power floated internal slab on greenguard insulation, drainage/servide works and external car parking and playground areas
52 Weeks
£1.5m
Private Residential Development
Yarnton
Construction of a new 10 plot private residential development, inclusive of all works up to and including slab level, road infrastructure works and drainage
46 Weeks
£800k
60 Bed Care Home
Benson
New build construction of a 60 bed care home with reinforced ground beams on driven piled foundations. Inclusive of all underground drainage/service works, externals package and extensive S278 package to existing lane
60 Weeks
£900k
80 Bed Care Homes
Crowthorne
New build construction of 80 bed care gome with pre-cast ground beam system on piled foundations. Inclusive of all underground drainage/service works and externals package
60 Weeks
£1m
Surestore
Wokingham
Construction of a new build surestore facility with external concrete yard and tarmac parking areas along with S278 package
42 Weeks
£600k
Eastern Avenue Ind estate
Dunstable
Construction of a multi unit development in an existing industrial estate with attenuation, permeable parking bays and concrete yards
42 Weeks
£400k
Beaconsfield Primary Care Centre
Beaconsfield
New build construction of a new primary care centre and onsite pharmacy including all substructure works and extensive permeable paving parking facilities
52 Weeks
£1.2m
Hinchley Wood Primary School
Esher
Construction of new building in place of fire damaged building for the primary school, including making good of all external areas etc
40 Weeks
£300k
Lucas Furniture
Aylesbury
Construction of flagship Lucas Furniture store with reinfirced ground beams on piled foundations and extenisve externals package
52 Weeks
£1m
31 plot residential development
Brightwell-Cum-Sotwell
New 31 plot residential development for private developer, consisting of multiple large detached family homes, road infrastructure works and all plot works
60 Weeks
£2.3m
Local Medical Centre
London Colney
New build medical centre with associated parking and new school tuff turf low impact car park construction
48 Weeks
£500k
L&D Bariatrics
Luton
Refurbishment works to L&D hospital including small extension and re-purposing of external areas
24 Weeks
£60k
Premier Inn Extension
Welwyn
Large multi room extension to an existing Premier Inn, consisting of all substructure works, drainage/services and external parking areas
28 Weeks
£250k
Royal Grammar School
High Wycombe
Conversion of existing courtyard into a student hub, with social spaces and canteen etc
16 Weeks
£100k
Richard Hale School, Sports Hall
Hertford
Construction of a new sports hall facility within the existing school grounds, inclusive of all additional drainage works etc
48 Weeks
£300k
Baxter Road
Newham
Construction of a block of flats and some single house dwellings for Newham council on and existing bronwfield site
52 Weeks
£400k
Woodbridge House
Uxbridge
Re-development and construction of existing Almshouse in the middle of Uxbridge providing new apartments for elderley residents
52 Weeks
£600k
Seaton Dr & Glenville Av
Aylesbury
Re-development of 2nr existing council garage sites into social housing. Full groundworks package undertaken inclusive of external works and S278 package
52 Weeks
£350k
Tungsten Trade Park
Brackley
Construction 2nr multi unit commercial buildings aong with a costa coffee.
30 Weeks
£1m
Xanadox Technologies HQ
Daventry
New headquarters with associated yard and parking space for a pharmaceutical company
22 Weeks
£350k
Segro Park
Bracknell
Speculative unit development on the SEGRO property in Bracknell, inclusive of large front yard and permeable parking facilities
36 Weeks
£900k
Broadoak Place - Reading University
Reading
externals works package inclusive of drainage and services works to complete the construction of a number of staff houses on the reading university campus
24 Weeks
£150k
Greenham Business Park
Thatcham
Construction of a 3 unit development in the heart of the Greenham Business park. Scheme included the installation of a large decorative stepoc retaining wall undertaken by Thamesbridge
40 Weeks
£900k
New Build Modular School
Swindon
Groundworks package for the construction of a new modular school on a new build housing estate. Works included pad and beam foundations with concrete plinths constructed to enable the placement of the mudular units
48 Weeks
£600k
70 Bed Care Home
Didcot
Construction of a new 70 bed care home with piled foundations, small localised patios, block paved access road and permeable parking facilites
62 Weeks
£600k
Premier Inn Extension
Enfield
Extension to an existing Premier inn, including adaption of existing parking facilities and forming a new site entrance
28 Weeks
£400k
Dog and Fox Pub
Wimbledon
Re-modelling of existing pub to provide new accomodation space. Works included the break-up of existing reinforced slab in very tight access conditions on Wimbledon High street
36 Weeks
£250k
Longcross Studios
Chertsey
Breaking up existing concrete yard space to enable the construction of a new stage/filming unit, inclusive of new yard slab facilities and fibre reinforced internal slabs
24 Weeks
£1.1m
Southend Hospital Mortuary
Southend
Reconfiguration of existing hospital mortuary, including substantial extension, with associated drainage and external works package
48 Weeks
£380k