Project Value – £2m
Project Duration – 78 Weeks
Project Description;
Large 24 bed hospice and associated staff ammenities
Scope of works;
- Piling mat with stabilisation geogrid
- Reinforced ground beams on piled foundations
- Extensive build-up of levels around the building footprint
- Restricted internal court yards
- Large bank re-grading
- Storm and Foul drainage installation including attenuation tanks
- 6m deep drainage connections to existing system
- Extensive external works package inclusive of block paving, slabbed patios and resin footpaths